AOA,
i am curious about relation between (splice length and development in RCC Beam Columns and footing) and earthquake zone. if i am using #8 bars then for fc'=3ksi and fy=60 ksi the development length is 71 inch and splice length is 92 inch (almost 7.5 ft). now normally overall story height is 10 ft minus beam depth of 1.5 ft , the net column height remains 8.5 ft . so actually i am providing 2 times of the actual reinforcement in columns. this seems reasonable for earthquake zone 3 and 4 where severe earthquake can occur. for seismic zone 2A and 2B this seems very over design . is there any material available for splice length , overlap and development length zone wise..