Øresund Bridge Connecting Sweden And Denmark

Recommended Posts

Assalam-o-alaikum,

Dear Colleagues!

The Øresund bridge is an engineering marvel that connects the Danish capital of Copenhagen to the Swedish city of Malmö.

A cable-stayed bridge runs nearly 8 km (5 miles) to an artificial island where it transitions into a tunnel that runs another 4 km (2.5 miles). The award-winning double-track railway and motorway opened on July 1, 2000.

For more details refer to the following link:

http://twistedsifter.com/2015/09/oresund-bridge-turns-into-tunnel-and-connects-denmark-and-sweden/

 

oresund-bridge-tunnel-1.jpg

oresund-bridge-tunnel-2.jpg

oresund-bridge-tunnel-3.jpg

Edited by engruzair

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now

Sign in to follow this  

  • Our picks

    • Dear Fellow Researchers, Academicians, and research students,

       

      NED University of Engineering & Technology in collaboration with Institution of Engineers Pakistan (IEP) is organizing 9th International Civil Engineering Conference (ICEC 2017) on December 22-23, 2017 at Karachi, Pakistan.

       The congress details are available at its website www.neduet.edu.pk/icec

       Also attached is congress flyer for information and dissemination among your peers.

       Abstracts submission deadline has been extended till October 31, 2017.

      Please click on the link to see the full description.
      • 0 replies
    • AoA all,

      Is it mandatory to do column concreting upto the soffit of the beam in a single pour ?

      What code says about the construction/cold joint location in column ?

      Majority of the contractors are pouring the column concrete upto the soffit of the beam (full height of the column), some contractors leave the column height about 9" to 12" below the beam level and then fill this 9" to 12" column height with the beams & slab concreting. On one site column concreting was stopped at the mid height and the remaining half was filled on the next day.

      Thanks

       

       
      • 5 replies
    • AOA 

      i am facing problems in shear wall design .what are the pier and spandral ?what will be the difference when we assign pier or spandral? without assigning these the shear wall design is incomplete .

      i am taking about etabsv16

      someone have document about shear wall design plz provide it 

      thank you

       
      • 9 replies
    • Salam Members,

      Congratulations to Engineers, PEC has become full signatory of Washington Accord, what are the benefits to Pakistani engineers for this agreement. 

       

      Regards   

       

       
      • 3 replies
    • Please clarify the following confusions one by one:-

       

      1. If we run P-delta analysis in ETABS, then should we ignore stiffness property modifiers for beams and columns? I have heard that if we perform P-delta analysis and apply stiffness modifiers at the same time then the moment magnification process is doubled...?

       

      2. ETABS considers selenderness of a column by applying moment magnification factors. If we run P-delta analysis also, does it mean that the selenderness of column is being over-estimated? I mean once the moments are magnified in P-delta analysis process and again through moment magnification process?

       

      Please help me understand the software myth and clarify above confusions.
      • 1 reply
    • Assalam o alaikum.
      According to ACI 12.5.2,
      development length for fc' = 3000, fy=60000, for normal weight concrete and epoxy less reinforcement, The required development length comes out to be
      for #3 = 8.2 inch
      for #4 = 10.95 inch
      for #6 = 16.42 inch
      for #8 = 21.9 inch
       
      And if in my case, ACI 12.5.3 is not fulfilled, it means now i have to provide ldh as mentioned above. ldh is STRAIGHT EMBEDMENT LENGTH + RADIUS OF BEND + ONE BAR DIAMETER as shown in figure attached. Now my question is, if in my case, main reinforcement of beam is of #6 and #4, minimum column size required will be 18 inch and 12 inch respectively. Lets say by any means, i can not select #4, #3 bars and size of column where bars are to be terminated is 12 inch, how to fullfil this development length???
      • 11 replies
    • Dear all,

      I am trying to design shearwalls through ETABS with temperature load applied over shell. At various location, spandral section fails in Shear due to temperature and piers (sometime in shear, mostly in flexure).  (See Attached Image)

      Certainly all the problem in Shearwalls are due to temperature. I don't want to increase cross section of spandral or pier at some location just due to temperature load case as it will appears non-uniform with rest of the wall. 

      I have seen stiffness modifier affect distribution of forces and also rigid/semi rigid daiphragm assumption. 

       

      Can anybody guide how to properly design the shear wall with temperature load applied in ETABS or share any similar experience. Thanks in Advance.    
      • 15 replies
    • ENGINEERS;
      I WILL LOOSE MY BRAIN FROM ETABS. 
      I DECIDED TO MAKE MANUAL MESHING FROM AREA ELEMENTS BESIDE EACH OTHER AND EVERY HING WAS FINE .
      BUT AFTER DEVISION SAY 7*7 ELEMNTS FOR EVERY BIG ELEMENT AND MAKING ETABS CHECH..................THEN 500 ERROR MESSAGE THAT ALL ELEMNTS ARE CLOSE TO EACH OTHER.  WHAT ARE GOING...... SOMEONE TELL ME PLEASE...... I WILL LOST MY WORK
      • 6 replies
    • Assalam o alaikum.
      I have just designed a frame structure with SMRF. The out put of shear seams weird to me. Column reports design shear Av/s as 0.045. (Images are attached). but when i right click the member, it must show me the most critical case HIGHLIGHTED AUTOMATICALLY. But it highlights load combo 38 (auto-generated combos have been used) which reports Av/s as 0.038. And 0.045 value is at combo 32. Is their any logic behind it?? More over how to interpret this Av/s?? means 0.045 in kip-in units means what? How can i convert this into spacing?? 
      • 9 replies
    • Hello everyone, I hope all of you will be fine. In etabs when we apply Response Spectrum loading on a multistoried building with 2 basement floors. At what floor level this loading will be applied as in equivalent static seismic analysis, we can apply EQX & EQY on any floor we like as this option is available in etabs but the problem is with response spectrum and time history analysis. please if someone knows and have the experince, share it i shall be very thankful.  
      • 5 replies
  • Recently Browsing   0 members

    No registered users viewing this page.

  • Similar Content

    • By hali
      Salam everyone.
      I'm doing a study for fatigue crack growth in a steel box girder bridge. For that I need the loading history (or strain history). If anyone can share it, it would be greatly appreciated.
       
      Regards,
      Haider Ali
       
    • By UmarMakhzumi
      Hello Everyone,
      Saw this on FB today. Thought would post. What do you think went wrong?
      Thanks.
       

    • By rummaan17
      Dear All, 
      I have designed the bridge between two building. Fixed at one end and roller at the other. The bridge at the roller end, rests on a concrete ledge. I have provided the expansion joint based on the formulation of ASCE for building separation. I have certain queries on it :
      1- Is building separation formulation is appropriate to provide expansion/moment joint in my case?
      2- I am trying to allow the movement through slotted holes in base plate. If my bridge required expansion is 300mm through formulation indicated in Point-1 above, should the slotted hole be twice of it i.e.  2x300mm = 600mm  
       
      I am still unsure as to what size the slotted hole should be ? and what governs the expansion joint of bridge over the ledge end. 
      I am relatively new to bridges. any help would be highly appreciated. Thanks in advance.
    • By waqar saleem
      Salam
      Girders of a bridge during launching collapsed. it is reported it happened due to heavy winds during launching of the girders,links for further details are attached.
      http://tribune.com.pk/story/1109218/rs330m-jhelum-bridge-collapses-ahead-inauguration/

      http://www.baaghi.tv/330-million-jhelum-bridge-collapsed-due-to-substandard-material-and-negligence-of-highways-department/
      Regards
    • By Ali Shan
      Can some body please give reference regarding torsional design of post-tensioned bridge girders? I have searched through AASHTO LRFD Bridge Design Specs but could not find a valid reference.
    • By saadyounas
      Hi guys
      In the question i have a super T girder with some reinforcement. Ques is I have to calculate compression strength in concrete block using formula C = gamma * 0.85 f'c * b (width)
      what value of b should i use to calculate this compressive force?
      thanks
      Saad

    • By ahmd8201
      Assalamualaikum dear forum members,
       
      I am currently designing a 35m span prestressed precast I beam bridge. The deck is formed from 300 rc insitu slab and the beams are 1.8m deep precast I beams. These span simply supported onto bearings shelf/abutment. Due to a high watertable, a secant pile wall option is used to form the abutments (with a hard/soft pile configuration). There is also a raft to form the underpass and act as a prop to the secant walls. 
       
      The secant walls are formed from 1200mm diam. piles and the raft is currently 2m deep. Apparently another engineer (quite senior) advised to have the raft dowelled into the piles, i.e. maybe 3 dowels per pile in the secant and then continued into the raft at an appropriate anchorage.
       
      The 35m span deck is supporting a curved road on top and the underpass is supporting 6 lanes of traffic. The whole bridge is designed to AASHTO
       
      I have a few issues which are troubling me which I would like to ask for opinions on;
       
       
      1) The prestressed I beams at ULS are sagging as they are simply supported. At SLS the ends are hogging; is this due to the prestressing force being too much? The secant pile wall is being designed by geotech. I assume that under any limit states as the deck is supported on bearings, the forces transferred to the secant will only ever be axial forces and shears ie. fx, fy, fz?
       
      2) The raft/ secant pile wall connection does not sound particularly convincing to me. The actual secant pile wall is very long and is about 480m. The raft slab therefore has movement joints every 10m or so. I thought that the raft plus secant could either be considered as an inverted portal frame or as a wall with a lateral prop. The senior engineer want to assume this is acting as an inverted portal frame but how can we have fully fixed moment connection with 3 dowel bars! Also if the abutment was actual wall, the raft could be detailed with rebar to be cast as a full moment connection, but with the secant the rebar will be very congested and I do not know an easier way to achieve this full moment connection of the raft with the secant. 
       
      Please advise.
    • By Nazish Fatima
      Has anyone done the wind analysis on bridges using British Standards ( BD 37/01). I have a few questions regarding its application on structure and live load both.
    • By muhammadrashid7
      Assalam O Alaikum Respected Members,
       
      Hope you all are doing good. Does anyone here know what is the procedure of bridge design. Or can anyone link me to any tutorial from where i can get guidance. I have a very basic understanding that too of the grillage design but want to know more about bridge design. 
       